1. Check manifolds for valve operation
2. Check the Actuators for correct operation
3. Check the circulating pumps for operation
4. Check flow rates (this is hard without more informatio Check Flow Temps via Thermal Imaging
• Check the Mixer Valves for correct operation
• Flush/Bleed underfloor heating pipework if required.
• Test all the electrical system and confirm the thermostats are working
• Fault find any electrical items that may not be working and correct.
• Check the operation of any motorised valves
• Check the boiler is engaging as and when it should be required
• Fix and replace any items I can there and then (if I have the parts on the van)
• Check anything else I can see that may need attention
• Carry out Thermal Imaging Report to confirm pipe operation